The 2025R1 write-back feature in Workday OfficeConnect — what it does, who can use it, how to set up a write-back workbook, and how to recover when it fails.
New in 2025R1 Write-back — submitting data from Excel cells back to Workday Adaptive Planning — became generally available in OfficeConnect 2025R1 (March 2025). It changes OfficeConnect from a one-way reporting surface into a two-way planning surface.

This guide is the canonical reference for write-back: the concept, what it can and can’t do, how to design a workbook for it, and what to do when something goes wrong.

What you’ll need:

  • Workday OfficeConnect 2025R1 or later
  • An Adaptive Planning tenant with at least one version that’s open for input
  • A user account with Input permission on that version
  • This article assumes you’ve already built basic OfficeConnect reports — start with Build Your First Report if not.

How write-back works

When data entry is enabled on a workbook, OfficeConnect formulas can be overwritten with typed values. Typing a number over an existing formula marks the cell as a pending input. Clicking Submit in the OfficeConnect ribbon sends every pending input to Adaptive Planning, where it persists in the target version.

After submit completes, the cell’s OfficeConnect formula is restored, and the next refresh resolves to the value you submitted.

What you can write back

TargetSupported?
Leaf-level intersections (single cost center + single account + single time period + single version)
Rollup accounts✗ — must be a leaf account
Rollup levels✗ — must be a leaf level
Aggregated time (e.g., a full quarter cell)✗ — must be a single period (month, week, etc., per your model)
Calculated / modeled accounts✗ — accounts whose value is computed from other accounts cannot accept input
Closed or locked versions✗ — version must be in input mode
Custom dimensions and Worktags✓ — when the underlying intersection is otherwise valid

If you submit to an invalid intersection, OfficeConnect returns an error per cell. See Common Write-back Errors.

Step 1 — Confirm the version is open for input

Write-back requires the target version in Adaptive Planning to be set to Input state. If it’s locked, submits will fail.

For admins & power users This check is usually done by an Adaptive Planning admin (or a power user with model-management permissions). Confirm with your admin that the version you’re writing to is in Input state for the time periods you need.

Step 2 — Enable data entry on the workbook

1
Open Workbook Properties In the OfficeConnect ribbon, click Workbook Properties.
2
Set Allow Data Entry to Yes In the Data Entry section, set Allow Data Entry to Yes. Click OK.

The Submit button in the ribbon is now active. OfficeConnect formulas in this workbook can be overwritten with typed values.

Step 3 — Build the input region

The full step-by-step is in Enter Budget Data, but the short version:

  1. Rows = leaf input accounts (one per row)
  2. Columns = single time periods (one per column)
  3. Headers = single version, single level, and any required custom dimensions

Use Cell Explorer on a sample data cell after refresh to confirm the intersection is a single, valid leaf. If Cell Explorer shows a rollup, your cell isn’t writable.

Step 4 — Enter values and submit

3
Refresh to load current values Cells populate with whatever’s currently in the version for each intersection.
4
Type new values Click any data cell and type a number. The cell highlights as a pending input.
5
Click Submit OfficeConnect pushes every pending input to Adaptive Planning. A confirmation dialog summarizes the result.

Step 5 — Verify

Click Refresh after submit. The cells you submitted should show your new values. If a cell reverts to a different number, an allocation rule, formula, or calculated account in Adaptive Planning has overridden your input — talk to your model administrator.

Designing for safe write-back

A few patterns make write-back workbooks safer to distribute:

  • One version per workbook. Mixing two input versions in one file is the fastest way to accidentally submit to the wrong one.
  • Lock non-input cells. Use Excel’s Protect Sheet to lock everything except the input region. See Lock and Protect Reports.
  • Show the version name on the sheet. A visible label like “Submitting to: Budget 2026 Draft” prevents misroutes.
  • Add a Cell Explorer reminder. Note in the workbook that planners should run Cell Explorer on any cell that doesn’t accept their input.
  • Pre-flight with a small region first. Submit 1-2 cells before submitting hundreds — confirms the path is open.

Common write-back errors

ErrorCauseFix
“Cannot write to non-leaf intersection”Cell resolves to a rollup account, level, or time periodReplace the element with its leaf-level child
“Version is locked”Target version is not in Input stateAsk the Adaptive admin to open the version
“Insufficient permission”User lacks Input on this version or levelAdjust permissions in Adaptive Planning
“Value overridden after submit”An allocation rule or modeled-account formula recalculated the cellSubmit at the source of the calculation, not the result
“Submit failed: timeout”Slow network or very large submit (hundreds+ cells)Split the submit into batches; see Optimize Performance

Governance: who should have Input permission?

Write-back grants users the ability to change planning data directly from Excel. Governance recommendations:

  • Production budget/forecast versions: restricted to designated planners per Level, with review/approval workflow in Adaptive Planning
  • Working drafts: broader Input access, snapshot to a locked version when finalized
  • What-if scenarios: in 2026R1+, use Personal what-if scenarios instead of granting Input to a shared version
  • Audit trail: every submit is logged in Adaptive Planning with timestamp + user. Review periodically.

Result

Your team can plan and re-plan in Excel without leaving the tool they live in. Workbook governance, version state, and Adaptive Planning’s permission model keep write-back from becoming a foot-gun.